Plant labor is not the constraining production factor.
Agreed. However, the plant won't add a C shift until there are parts and everything else in line to make three shifts run. I figure if they have added the C shift, they've solved the other issues.
 

RonTCat

Well-Known Member
First Name
Ron
Joined
Jul 21, 2020
Threads
27
Messages
1,110
Reaction score
2,927
Location
USA
Vehicles
Mach-E wannabuy
Country flag
Agreed. However, the plant won't add a C shift until there are parts and everything else in line to make three shifts run. I figure if they have added the C shift, they've solved the other issues.
Plants operate most effectively on two shifts. You need about 2 hours/day to fix everything that broke in the prior 22. You can easily get 22hrs/day from 2 shifts with O/T. Not forever, but long enough to plan your way out of overwhelming demand.

A third shift really indicates you want to run the plant 24/7 to push through a huge demand that can be supported with part supply, but adding additional plants isn't immediately feasible. 3 shifts not being optimal, the system will always settle back to a 2 shift system whenever possible.

This might explain why Ford Manufacturing leadership has indicated 3 shifts is not on the table for Mach-e. The situation does not fit the 3-shift criterion, and likely won't for quite a while.
 
OP
OP
ChasingCoral

ChasingCoral

Well-Known Member
First Name
Mark
Joined
Feb 3, 2020
Threads
376
Messages
12,403
Reaction score
24,517
Location
Maryland
Vehicles
GB E4X FE, Leaf, Tacoma, F-150 Lightning ordered
Occupation
Retired oceanographer
Country flag
Plants operate most effectively on two shifts. You need about 2 hours/day to fix everything that broke in the prior 22. You can easily get 22hrs/day from 2 shifts with O/T. Not forever, but long enough to plan your way out of overwhelming demand.

A third shift really indicates you want to run the plant 24/7 to push through a huge demand that can be supported with part supply, but adding additional plants isn't immediately feasible. 3 shifts not being optimal, the system will always settle back to a 2 shift system whenever possible.

This might explain why Ford Manufacturing leadership has indicated 3 shifts is not on the table for Mach-e. The situation does not fit the 3-shift criterion, and likely won't for quite a while.
That certainly makes sense. You've got to fix things at some point!
 

GoGoGadgetMachE

Well-Known Member
First Name
Michael
Joined
Jan 23, 2020
Threads
153
Messages
5,614
Reaction score
12,654
Location
Ohio
Vehicles
2021 Mach-E 1st Ed., 2022 Lightning Platinum
Occupation
Professional forum cheerleader and fanboy
Country flag
That certainly makes sense. You've got to fix things at some point!
see if Ford was a modern company they'd fix all those factory problems with simple OTA updates. (*)