Update on Mach-E launch progress from engineering friends in Mexico

RVAtom

Well-Known Member
First Name
Adam
Joined
Jul 21, 2020
Threads
26
Messages
207
Reaction score
309
Location
RVA
Vehicles
Mustang Mach E
Country flag
Their record for one shift off the Final line is like 20
So don’t hold your breath but maybe

20 a hour
400 a day maybe?


20 per shift

20 per shift dear lord

...

You better come down here and start cracking the whip Lol. You worked the truck and navaigator launch to a T we could of used you down here.
I may be late to the party, but I think we know that @trutolife27 is/was an employee of Ford, is that correct? I take from this exchange that he also may have been involved with getting manufacturing going on a new model of vehicle or two in the past. With those assumptions I have a question about auto manufacturing.

How does the beginning usually go with an assembly line? Is it normal for things to just run really slowly to make sure the quality is good? Am I right in assuming that maybe they are running things extra slow to make sure they get things right for now? I am thinking maybe if this were the first few days of a compliance car, there would be a little more of a "that's good enough, keep 'em going" attitude.

Do they check things like panel gaps and alignment as they go and reject/redo assembly parts from time to time as the assembly line gets going?
 

GregM

Well-Known Member
First Name
Greg
Joined
Mar 11, 2020
Threads
5
Messages
195
Reaction score
197
Location
Virginia
Vehicles
Audi A3, Tahoe, Mustang Mach E Premium (on order)
Occupation
Communications/Marketing
Country flag
If they have extra parts, I wouldn't mind upgrading my Premium to have red brake calipers...
 

methorian

Well-Known Member
Joined
Nov 18, 2019
Threads
17
Messages
1,557
Reaction score
2,437
Location
Roanoke, VA
Vehicles
2021 Mach-E First Edition, 2025 Kia EV6 GT-Line
Occupation
IT Admin
Country flag
If they have extra parts, I wouldn't mind upgrading my Premium to have red brake calipers...
You can call and possible upgrade now - 844.802.6634 per Ford Instagram post.
 


GoGoGadgetMachE

Well-Known Member
First Name
Michael
Joined
Jan 23, 2020
Threads
153
Messages
5,612
Reaction score
12,669
Location
Ohio
Vehicles
2021 Mach-E 1st Ed., 2022 Lightning Platinum
Occupation
Professional forum cheerleader and fanboy
Country flag
I guarantee Michigan won't lose this year!
It genuinely amazes me as an Ohio transplant that all of the Michigan-Ohio nonsense started with "We Want Toledo!"

(yes I know why, but it is still amusing to me as someone living in 2020.)
 

JamieGeek

Well-Known Member
Joined
Dec 29, 2019
Threads
82
Messages
3,589
Reaction score
6,823
Location
Southeastern Michigan
Website
spareelectrons.wordpress.com
Vehicles
Escape PHEV, old: Mach-E, Bolt, C-Max Energi, Focus Electric
Country flag
It genuinely amazes me as an Ohio transplant that all of the Michigan-Ohio nonsense started with "We Want Toledo!"

(yes I know why, but it is still amusing to me as someone living in 2020.)
Yeah I don't know why people in MI are sore about it, we got the UP for not getting Toledo (and, honestly, I think I like the UP better than Toledo ;) ).
 
OP
OP
trutolife27

trutolife27

Well-Known Member
Joined
Jul 13, 2020
Threads
127
Messages
3,266
Reaction score
13,888
Location
Bourbon Country.
Vehicles
Lincoln mkx , Ford f-150, Mache
Country flag
I may be late to the party, but I think we know that @trutolife27 is/was an employee of Ford, is that correct? I take from this exchange that he also may have been involved with getting manufacturing going on a new model of vehicle or two in the past. With those assumptions I have a question about auto manufacturing.

How does the beginning usually go with an assembly line? Is it normal for things to just run really slowly to make sure the quality is good? Am I right in assuming that maybe they are running things extra slow to make sure they get things right for now? I am thinking maybe if this were the first few days of a compliance car, there would be a little more of a "that's good enough, keep 'em going" attitude.

Do they check things like panel gaps and alignment as they go and reject/redo assembly parts from time to time as the assembly line gets going?
during Launch the line is slowed way down and slowly speed back up tell the right JPH are meet.
When models change over so does the jobs on the lines. Parts start being put on in different areas jobs change who put on what part, jobs added here take here. Its a long process.

They have to make sure when the body style changed so does the line so it does not effect the efficiently. Your automobile manufacturers hire company's in Detroit like kuka, valiant, and others to set up the lines and test the process build, and the sub assembly's.

Then you would make 10 to 15 a day ship them to the plant they go to aka Chicago, saint Louis, Michigan, Kentucky. When there the body shell would go down the line and finished building paint, trim, engine, chassis, frame. Everything has to be check and if wrong info sent back up to Detroit to fix. Water leaks, baffles, aero problems, sealer. List goes on and on.

Its a long process. But a plant like the mach-e is all down there, there was not a product in the way. The plant was cleaned out and retooled. Kinda like a brand new plant.

Here is some videos at the plant i work.





 

jhalkias

Well-Known Member
First Name
John
Joined
Mar 3, 2020
Threads
123
Messages
2,491
Reaction score
5,039
Location
Ohio
Vehicles
'21 RR ME FE, '22 Corsair GT, '22 Lightning Lariat
Occupation
Benefit Fund Administrator
Country flag
during Launch the line is slowed way down and slowly speed back up tell the right JPH are meet.
When models change over so does the jobs on the lines. Parts start being put on in different areas jobs change who put on what part, jobs added here take here. Its a long process.

They have to make sure when the body style changed so does the line so it does not effect the efficiently. Your automobile manufacturers hire company's in Detroit like kuka, valiant, and others to set up the lines and test the process build, and the sub assembly's.

Then you would make 10 to 15 a day ship them to the plant they go to aka Chicago, saint Louis, Michigan, Kentucky. When there the body shell would go down the line and finished building paint, trim, engine, chassis, frame. Everything has to be check and if wrong info sent back up to Detroit to fix. Water leaks, baffles, aero problems, sealer. List goes on and on.

Its a long process. But a plant like the mach-e is all down there, there was not a product in the way. The plant was cleaned out and retooled. Kinda like a brand new plant.

Here is some videos at the plant i work.





Love this stuff. Used to tour the Canton Ford Forging plant when I was a kid and dad worked there. Open house was always a highlight of the summer. Thanks for bringing back good memories.
 

GoGoGadgetMachE

Well-Known Member
First Name
Michael
Joined
Jan 23, 2020
Threads
153
Messages
5,612
Reaction score
12,669
Location
Ohio
Vehicles
2021 Mach-E 1st Ed., 2022 Lightning Platinum
Occupation
Professional forum cheerleader and fanboy
Country flag
Love this stuff. Used to tour the Canton Ford Forging plant when I was a kid and dad worked there. Open house was always a highlight of the summer. Thanks for bringing back good memories.
I know a guy that used to work in the Brook Park plant. He gave me a tour once. I owned my 1995 Mustang GT convertible at the time. At one point he pointed and said, "that is where your engine was built." I still get excited remembering that.
 

timbop

Well-Known Member
First Name
Tim
Joined
Jan 3, 2020
Threads
65
Messages
6,832
Reaction score
14,036
Location
New Jersey
Vehicles
Solar powered 2021 MME ER RWD (CA RT1)
Occupation
Software Engineer
Country flag
during Launch the line is slowed way down and slowly speed back up tell the right JPH are meet.
When models change over so does the jobs on the lines. Parts start being put on in different areas jobs change who put on what part, jobs added here take here. Its a long process.

They have to make sure when the body style changed so does the line so it does not effect the efficiently. Your automobile manufacturers hire company's in Detroit like kuka, valiant, and others to set up the lines and test the process build, and the sub assembly's.

Then you would make 10 to 15 a day ship them to the plant they go to aka Chicago, saint Louis, Michigan, Kentucky. When there the body shell would go down the line and finished building paint, trim, engine, chassis, frame. Everything has to be check and if wrong info sent back up to Detroit to fix. Water leaks, baffles, aero problems, sealer. List goes on and on.

Its a long process. But a plant like the mach-e is all down there, there was not a product in the way. The plant was cleaned out and retooled. Kinda like a brand new plant.

Here is some videos at the plant i work.





Awesome! Thanks for posting!
 

ChasingCoral

Well-Known Member
First Name
Mark
Joined
Feb 3, 2020
Threads
502
Messages
14,306
Reaction score
28,655
Location
Maryland
Vehicles
2021 GB E4X FE, 2022 F-150 Lightning Lariat ER
Occupation
Retired oceanographer
Country flag
during Launch the line is slowed way down and slowly speed back up tell the right JPH are meet.
When models change over so does the jobs on the lines. Parts start being put on in different areas jobs change who put on what part, jobs added here take here. Its a long process.

They have to make sure when the body style changed so does the line so it does not effect the efficiently. Your automobile manufacturers hire company's in Detroit like kuka, valiant, and others to set up the lines and test the process build, and the sub assembly's.

Then you would make 10 to 15 a day ship them to the plant they go to aka Chicago, saint Louis, Michigan, Kentucky. When there the body shell would go down the line and finished building paint, trim, engine, chassis, frame. Everything has to be check and if wrong info sent back up to Detroit to fix. Water leaks, baffles, aero problems, sealer. List goes on and on.

Its a long process. But a plant like the mach-e is all down there, there was not a product in the way. The plant was cleaned out and retooled. Kinda like a brand new plant.

Here is some videos at the plant i work.





Great response. Thanks for the quick lesson.

Here's a gymnastics analogy. Give Dominique Dawes a brand new floor routine, including a couple of new moves. It will take her weeks to get it down, months to perfect it. Even longer if she goes to a "first ever" move and will have to spend weeks on that one move alone.

We all want our cars to be perfect.